Suit filed against Bank of America over alleged failure to disburse TARP funds

A Seattle law firm, Hagens Berman Sobol & Shapiro, has filed a lawsuit against Bank of America over its apparent failure to satisfactorily distribute TARP funds to stem foreclosures. 

According to a press release by Hagens Berman, Bank of America has made an "affirmative decision to slow the loan modification process for reasons that are solely in the bank's financial interests."

It will be interesting to monitor how this suit develops, as it strikes at the core issue of whether the government's injection of capital into the banking market actually resulted in a positive result. 

If at first you don't succeed, try, try again! The federal government takes another shot at curbing the foreclosure crisis

After the first attempt by the Obama Administration to stem the foreclosure tide fell flat (only a fraction of eligible home owners facing foreclosure secured permanent modifications), the federal government is proposing a broad new initiative.

The New York Times reports that the government will now try to reduce the principal for home loan modifications.  To do this, it intends to provide a program by which those who are "underwater" (home value less than what is owed) can refinance into a government-backed mortgage.

This is significant because most (if not all) loan modifications up to now consisted of banks largely shifting interest rates and extending payment terms.  Thus, the actual principal of the loan was never really effected, merely the interest.  As a result, the underlying problem which plagued a lot of homeowners was never truly addressed (that they simply had purchased homes which were beyond their budget). 

To fund this new program, the government intends to utilize $50 billion funds previously allotted to the Troubled Asset Relief Program, more commonly known as "TARP."  Though reaction from many non-profit groups is generally positive, it remains to be seen whether banks will cooperate with the new program. 

How subcontractors, laborers, mechanics, and suppliers are protected on public projects by RCW 39.08

Public and private construction projects are different in many respects, however chief among those differences is the party that owns the property subject to the contract.  In other words, when contractors enter into a contractor with a municipality (County, City, State, agency, etc.) any subcontractors, material suppliers, laborers, or mechanics to that project are at a disadvantage.  Why, you ask?  Because unlike private property, the law prohibits subcontractors, material suppliers, laborers, and mechanics from recording liens on public property.

This is important because these second-tier contract participants are therefore unable to protect themselves should the general contractor refuse to pay them for their services.  Unfortunetly, this puts them in an impossible position, as they cannot gain payment through a lien on public property, but there is often little to no amount left in the general contractor's construction bond that would satisfy what these subcontractors are owed. 

In response to this issue, Washington State enacted RCW 39.08, a statute which extends certain protections to subcontractors, laborers, material suppliers, and mechanics who do work for a general contractor on a public project.  Here is what it does:

RCW 39.08.10 -- Municipalities must require that general contractors to public projects have a "good and sufficient bond."  This bond is to be filed with the clerk or comptroller and is intended to stand as a surety in case the general neglects payment to all "laborers, mechanics, and subcontractors and material suppliers..."

RCW 39.08.15 -- If the bond is not present, or is insufficient, then the municipality becomes "liable to the [laborers, mechanics, and subcontractors and material suppliers] to the full extent and for the full amount of all such debts so contracted by such contractor."

The case law supports these protections --

Puget Sound Elec. Workers Health and Welfare Trust Fund v. Merit, 123 Wash. 2d 565, 870 P.2d 960 (1994) states that public works lien statutes require general contractors on public projects execute and deliver a bond to the public agency in order to protect all laborers, mechanics, subcontractors, and material suppliers performing the contract work.

National Sur. Co. v. Bratnober Lumber Co., 67 Wash. 601, 122 P. 337 (1912) states that statutory requirements for contractors on municipal improvements give bonds for payment of laborers and materialmen in order to secure claims not protected by lien laws.

Smith v. Town of Tukwila, 118 Wash. 266, 203 P. 369 (1922) also states that if the bond does not meet the statutory requirements, then it is insufficient and not a statutory bond (which by implication would satisfy the requirements outlined in RCW 39.08).

In short, if you are a subcontractor, laborer, material supplier, or mechanic doing work on a public job, and the general contractor refuses to pay your invoices, look to the contractor's bond.  If it is insufficient, then you may have a claim against the city/county/state is paying for the project. 

 

Liquidated damages clauses in construction contracts

If you are ever involved in property development, a liquidated damages clause is something you ought to be familiar with.  What is a "liquidated damage"?  It is basically an amount of damage that contracting parties agree to during the formation of the contract, which is applied if the agreement is breached.  In other words, rather than the parties trying to calculate damages after a breach happens, they pre-determine the damage amounts.

These clauses are usually favored and often upheld in Washington State.  Ashley v. Lance, 80 Wash. 2d 274, 280, 493 P. 2d 1242, 62 A.L.R. 3d 962 (1972).  To determine whether they are enforceable, Washington courts generally require the following two factors to be satisfied:

(1) Liquidated damage must be reasonable (just compensation for the harm caused by the breach);

(2) It must be very difficult or impossible to determine the harm beforehand.

Walter Implement, Inc. v. Focht, 107 Wash. 2d 553, 559 (1987). 

A liquidated damages clause will NOT be upheld if it is show that the provision is simply a penalty or is otherwise unlawful.  Jenson v. Richens, 74 Wash.2d 41, 47, 442 P.2d 636 (1968). 

In short, parties can pre-set what a contract breach will cost the breaching party.  This allows for a clear assessment of damages, provided that it is not a penalty.  The liquidated damages must not only be reasonable when compared to the harm of the breach, but the harm caused must be difficult or impossible to ascertain.